In response to the community survey, Table 6.1, Top Priority Projects, and Table 6.2, Project Considerations,
consolidate several project initiatives to reflect findings from the community preference survey and to
accommodate the natural sequencing of design and programming elements. In addition to generalized short- (1
to 2 years), mid- (3 to 4 years), and long-term (5 or more years) implementation schedules, leading entities are
also identified for each initiative.
Table 6.1, Top Priority Projects
Years
Rank Projects and Programs Lead Entities
1 - 2 3 - 4 5+
CDC, City,
TxDOT,
1 Esplanade Streetscape Improvements
(Proposed)
Main Street
Determine the scope and prioritization of all potential streetscape
improvements. As proposed in this plan, address marked cross-
walks, corner bump-outs, stylized lighting, and other streetscape
accents that improve the safety, appearance, and functionality of
Esplanade Street.
Continue coordinating with TxDOT to identify funding availability,
sequencing, and design parameters for potential streetscape
improvements.
Prepare a detailed Esplanade streetscape plan which includes
itemized cost estimates and incremental phases. Include the site
selection, design, and cost of off-site parking lots as needed.
Develop a five-year strategic implementation plan, which
will address sequencing, funding, design, and construction
timeframes.
Produce annual status reports to share with project partners,
which will help to maintain project momentum and coordinate
unanticipated challenges.
Solicit sponsorship opportunities (e.g., tree dedications,
streetscape benches, monumentation) to offset the cost and
maintenance of improvements.
Implement a comprehensive funding strategy for designing,
constructing, and maintaining the streetscape improvements.
Explore options for tax increment financing, developer
concessions, special assessments, and a private maintenance
endowment to offset the City's investments.
CDC, City,
(Proposed)
2 Farmers Market Relocation
Main Street,
Chamber
Establish a steering committee with Farmers Market stakeholders
to confirm interest in relocation; identify space and facility needs;
and solicit the involvement of project champions.
ADOPTED 03.04.13 31