5.6 Order of Magnitude Costs



                 The cost estimate for the construction of all proposed raised
                 medians and dividers along US Highway 421 and S. Frankiln
                 Street, and includes saw-cutting, demolition and removal of
                 asphalt pavement and subbase material; the construction of
                 contrete curbs and gutter, backfilling and stabilization; and the
                 installation of small street trees.






                 Table 5.6.10 Raised Medians along US Highway 421 / S. Franklin Street

                  Table 5.6.10 Raised Medians along US Highway 421 / S. Franklin Street
                                                         Raised Median A:  Raised Divider B:  Raised Median C: Raised Divider D: Raised Divider E:  Raised Median F:  Raised Median G: Raised Median H:
                 Item Description                        Walmart Drive to  Menards Entrance  Larkspur Lane to  Lowes Entrance   Big R Driveway to  Dunes Plaza Entry  US Highway 20 to Kintzele Road to
                                                         Lowes Entry Drive  to Larkspur Lane  Lowes Entrance   to Big R Driveway Meijer Drive  to US Highway 20  Kintzele Road  St. John Road

                  General
                  Construction Engineering (15%)         $6,578        $2,100        $5,715        $2,119       $1,695        $4,852        $7,282        $4,380
                  Mobilization/Demobilization (5%)       $2,193        $700          $1,905        $706
                  Clearing ROW (2%)                      $877          $280          $762          $283         $226          $647          $971          $584
                  Erosion Control (1%)                   $439          $140          $381          $142         $113          $323          $485          $292
                  Maintenance of Traffic (2%)            $877          $280          $762          $283         $226          $647          $971          $584
                  Landscape Enhancements (5)             $7,500        $3,000        $5,000                     $1,000        $4,500        $3,000        $1,000
                  Total (in 2015 dollars)                $51,350       $17,000       $43,100       $14,125      $12,300       $36,850       $51,550       $30,200
                  Contingency (20%)                      $10,270       $3,400        $8,620        $2,825       $2,460        $7,370        $10,310       $6,040
                  Grand Total                            $61,620       $20,400       $51,720       $16,950      $14,760       $44,220       $61,860       $36,240
                 (1)    Extension of Ohio Street south (CR 1050 W) to Interstate 94 ROW: two lane road (25 ft. width) approx. 2,500 lin. feet (62,500 sq. ft.)
                 (2)    Area of roadway = 62,500 sq. ft.
                 (3)    Area of disturbance = 25 ft. on either side of roadway (total area; 125,000 sq. ft.)
                 (4)    Total approximate length: 2,500 lin. ft. ($76 per lin. ft = 10’ wide, on 6” compacted stone subbase, 2 ft. of earthwork, stabilization
                 (5)    Landscape enhnacements include small, evergeen trees, 10 ft. O.C.; ornamental grasses, finish grading and mulching (lump sum)



























                                                                                                                                                                                                                                     5-69

                                                                                                                                                                                Adopted: August 16, 2016          Implementation  5.0