Page 38 - Valparaiso, IN U.S. 30 Corridor Plan
P. 38

Adopted July 25, 2011
 PG 24
 Haymarket                                       The 49 Gateway PG 18

 The swath of former industrial land roughly
 between Washington and Campbell Streets         From a regional transportation standpoint, the Highway 30/ SR-49 interchange
 could be repurposed for a combination of        is Valparaiso’s de facto “front door” and main crossroads.
 small, clean production activities along with
 some limited residential uses.


                                                                                8   Potential overpass design






 4  7  9
 5

 6






              8









 The Trestles PG 21                                                                 9   Monument signage




 This ½-mile segment is the most environmentally constrained
 section within the corridor with a steep ridge on the north side of   6  Railroad crossing
 the highway and wetlands to the south.                              PG 20
                                                   Campus Drive

 3  4  6                                           This area should be designed as a verdant parkway
                                                   winding its way between two prominent landscape
                                                   features along the corridor. An overhead bike-ped
                                                   bridge should connect across the highway in the
                                                   vicinity of the Sturdy Road intersection.


                                                                                          7  Pedestrian-bike bridge
 5  Stream culvert crossing














                                                                                                            13