Page 80 - Valparaiso, IN U.S. 30 Corridor Plan
P. 80
Adopted July 25, 2011
5-Year Planning Goals
Tracks 2011-2012 2013-2014 2015-2016 2017+
1. Legal/Regulatory
• Outreach
a. Zoning & Design Guidelines • Amendment drafting
• Resolution, adoption
• Meetings with City
b. ETJ Authority • Filings, notices • Implementation
• Public hearings
c. Annexations • Pre-annexation draft language • Ongoing with service extensions
2. Direct Public Investment
• Phase 2 Construction (east
• Design and engineering • Phase 1 construction (Wash
a. Streetscape gateway) Phase 3 con-
• Peg. funding sources @ US 30)
struction (west gateway)
• Blight study • TIF project plan
• Statutory redevelopment plan • Infrastructure needs incor- • Land assembly • Land assembly
b. TIF District (Wash @ US 30) • Sitework
• Meetings with property owners, porated in to CIP • Developer recruitment • Developer recruitment
taxing bodies • District creation
• Preliminary design of
• Engineering construction
• Coordinated with other devel- • Begin preliminary alterna- major intersection im-
c. Infrastructure tives analysis on Silhavy provements: Sturdy Rd.,
opment and incorporate into realignment Washington St., and
CIP
Hayes-Leonard Rd.
d. Underground wires Coordinated with infrastructure work and private development
e. Salt Creek restoration &
stormwater management plan • Grant procurement • Planning • Implementation
3. Incentives
• Peg. funding sources
a. Façade grants • Establish eligibility criteria
• Program launch
• Concept white paper • Fund-raising
b. Hwy 30 loan fund • Recruit fund-raisers • Underwriting criteria • Program launch
• ID funding sources
4. Privately-led Initiatives
a. VU Joint Maintenance
agreement • MOU VU maintenance of Campus Drive segment
• Business owner outreach • Formation of business as- • Creation of BID district
b. Hwy 30 Business Association • Maiden project launch
meetings sociation • BID plan